Stoppage: Worcester & Birmingham Canal
Lock 4 on the Worcester & Birmingham Canal
Wednesday 19 June 2013 – Wednesday 19 June 2013
There will be an emergency stoppage between 6.00am and 10.00am to investigate a problem with the back pumping system.
Canal and River Trust apologise for any inconvenience this may cause
Enquiries: 0303 040 4040
Restriction: Cannock Extension Canal
Pelsall Junction
Friday 7 June 2013 – Friday 14 June 2013
Due to dredging activities a silt curtain will be installed at Pelsall Junction, restricting navigation to/from the Cannock Extension Canal. Boats will be unable to pass between 9am and 2pm on the below dates:
Friday 7th June
Monday to Friday 10th – 14th June
Canal & River Trust apologise for any inconvenience this may cause.
Enquiries: 0303 040 4040
Restriction: River Trent
Marton Mill Waste Site and Cromwell Lock
Thursday 30 May 2013 until further notice
Land & Water working on behalf of the Canal & River Trust will be dredging the River Trent between Marton Mill and Cromwell Lock.
The scope of the dredging will also include Torksey Cut.
We apologise for any inconvenience this may cause but this work is very important ensuring the navigable channel is maintained.
Craft operators should be aware of the likelihood of passing the dredger & associated craft and follow any instructions from the crews where appropriate.
The lockkeepers at Cromwell and Torksey will be able to provide up to date information about the current location of the dredging works.
Alternatively, please contact Paul Fox, CRT Project Manager on 0303 040 4040.
Enquiries: 0303 040 4040.
Stoppage: Wyrley & Essington Canal
Pelsall Works Bridge to Yorks Bridge, Pelsall Common
Friday 14 June 2013 – Monday 17 June 2013
Towpath mooring between Pelsall Works Bridge and Yorks Bridge will be suspended from 14th to 17th June due to the Pelsall Canal Festival taking place. Mooring against the towpath will be managed by the organisers of the festival.
Canal & River Trust apologise for any inconvenience this may cause.
Enquiries: 0303 040 4040
Advice: Staffordshire & Worcestershire Canal
Kinver Sanitary Station
Tuesday 28 May 2013 – Thursday 30 May 2013
UPDATE (30 May 2013): The pump has now been repaired and the sanitary station is fully operational.
Advice: Staffordshire & Worcestershire Canal
Kinver Sanitary Station
Tuesday 28 May 2013 until further notice
Kinver Sanitary Station will be unavailable with immediate effect due to a pump failure. We aim to get this repaired as soon as possible and will update accordingly.
Canal & River Trust apologise for any inconvenience this may cause.
Enquiries: 0303 040 4040
Amended Stoppage: River Trent
Cromwell Lock
Thursday 16 May 2013 – Friday 31 May 2013
UPDATE (22 May 2013): Following on from our stoppage notice of the 16th May, we are now able to advise that, following the completion of some of the dredging works required and an inspection this afternoon, passage through Cromwell Lock will be possible from Saturday 25th May to Monday 27th May. The lock will be manned from 06.00h – 21.00h on each of these three days.
Until then and from Tuesday 28th May, the original stoppage notice closing the navigation until the 31st May will remain in force to allow us to complete the works.
Towpath Closure only: Grand Union Canal
Hunton Bridge to Cassiobury Park
Monday 3 June 2013 – Monday 10 June 2013
Due to an event in this vicinity, the towpath will be closed and all moorings suspended between Bridge 162B, Sparrows Hearne and Bridge 166, Grove Mill Footbridge from Noon (12pm) on Monday 3rd June to Noon (12pm) on Monday 10th June 2013.
There will be no entry to this section of towpath from any access point between bridges 162B and 166.
Boats will be able to navigate through the area but no boats can stop or moor, at any time, between these bridges for the full period of the restriction. Any boat which is moored in the area must have commenced moving out of the closure zone by 8am on Monday 3rd June 2013.
The towpath is also closed
Enquiries: 0303 040 4040
River Servern River Levels
Thursday 16 May 2013 until further notice
Please be advised that due to rapidly rising River levels on the River Severn Upper Lode Lock is now closed to navigation and the remainder of the River Severn is in amber alert.
Restriction: Worcester & Birmingham Canal
Visitor Mooring at Upton Upon Severn, River Severn
Tuesday 14 May 2013 until further notice
Dear Boaters,
We have given our consent for the passenger boat Avon Belle to board and disembark passengers from the visitor mooring at Upton this season. Newly introduced restrictions on coaches passing through the town mean that the operators can no longer take coach parties at their home mooring downstream of the town centre. The designated coach park is right opposite the visitor mooring, so this is a very useful pick up point for parties arriving by coach. The operators will put up signs on the mooring advising when they are going to be picking up/setting down. The boat will continue to be moored downstream, below the town, when not in use.
They will not use the mooring at all during the jazz and blues festivals. The marina (just downstream of the town bridge, on the opposite side of the river to the visitor mooring) offers visitor mooring should you find the moorings full at any time. This is a one year trial. If you have any comments or suggestions, please contact me.
Thank you very much for your co-operation.
Susie Mercer, Boating Trade Manager. Tel: 01452 318012 Email: susie.mercer@canalrivertrust.org.uk
Enquiries: 01452 318012
Stoppage: River Trent
Cromwell Lock
Friday 10 May 2013 – Saturday 18 May 2013
Following on from the advice notice concerning the presence of sand bars at points on the River Trent, we have today taken the decision to close the River Trent at Cromwell Lock.
These sand bars arose from the floods of last year and over the past few days, the sand bar at Cromwell has developed to such an extent that we are now unable to guarantee safe passage for boats exiting or entering Cromwell Lock.
Although dredging works were planned to take place later this month at Cromwell, we will today divert resources from other works to the lock with the intention of commencing dredging as soon as possible.
Although the speed of resolving this issue is somewhat tide dependant, and somewhat exasperated by low rainfall, we will do what we can to allow passage through the lock from next Saturday, the 18th May.
We apologise for any inconvenience this may cause and fully intend to resolve the situation as soon as possible.
These initial works to reopen the navigation will be followed by major dredging at this and several others sites on the River Trent over the coming months. We will keep boaters updated as the works progress.
Enquiries: Newark – 0303 040 4040
Stoppage: Trent & Mersey Canal
Ground paddle repairs
Monday 13 May 2013 – Monday 13 May 2013
Lock Stoppage whilst installing repaired ground paddle and carrying out repairs to damaged framework
Lock 43 top gate offside ground paddle
Re-install repaired ground paddle and repair paddle framework.
We aim to get the repairs carried out within a 4 hour time frame on the morning of the 13th of May 2013
Canal & River Trust apologise for any inconvenience caused
Enquiries: 03030 404040
Stoppage: Shropshire Union Canal
TREE BLOCKING CANAL @ BRIDGE 29 Nr GNOSALL
Thursday 9 May 2013 – Friday 10 May 2013
UPDATE (10 May 2013): Contractors have attended site and with the assistance from the Canal & River Trust Team have cleared the tree and the canal is now fully navigable.
The Canal & River Trust apologise for any inconvenience caused and thank you for your patience whilst the tree was being cleared.
Restriction: Shropshire Union Canal
TREE PARTIALLY BLOCKING CANAL @ BRIDGE 20 (DIRTY LANE)
Thursday 9 May 2013 – Friday 10 May 2013
UPDATE (10 May 2013): The tree has been cleared and the canal is now open at this location.
The Canal & River Trust apologise for any inconvenience caused.
Stoppage: Shropshire Union Canal
TREE BLOCKING CANAL @ BRIDGE 29 Nr GNOSALL
Thursday 9 May 2013 until further notice
There is a large tree blocking the canal at Bridge 29 (Wood Eaton Bridge), south of Gnosall.
Contractors have been called and the tree will be removed as soon as possible and a update will follow as soon as available.
The nearest winding hole if travelling from the North is located at Norbury Wharf or if travelling from the south between bridge 25 & 26
The Canal & River Trust apologise for any inconvenience caused.
The towpath is also closed
Restriction: Grand Union Canal
Winkwell Swingbridge 147
Tuesday 7 May 2013 – Tuesday 7 May 2013
UPDATE (07 May 2013): Please be advised that the bridge has been fixed and is fully working with immediate effect.
Restriction: Grand Union Canal
Winkwell Swingbridge 147
Tuesday 7 May 2013 until further notice
The Winkwell Swingbridge has a mechanical failure and can only be opened manually by canal & River Trust staff. Staff will be at winkwell Swingbridge at 9am, 12 noon and 4pm to open the bridge, outside of these times you will not be able to pass through the bridge. Please wait for Canal & River Trust staff to be at site and assist you with the bridge.
Enquiries: 0303 0404040
Restriction: River Trent
Stoke Lock
Wednesday 1 May 2013 until further notice
The flood events over the last 12 months have caused a build-up of silt at several locations along the River Trent.
Our major works team have allocated £500,000 to tackle this issue and will start dredging in May.
This work will be undertaken alongside works to clear the lock tails by the Crane Boat.
The worst affected areas currently include downstream of Cromwell Lock, downstream of Stoke Lock, downstream of Newark Town Lock, downstream of Hazleford Lock and Torksey Cut.
We apologise for any difficulties this may cause and ask you to take advice from the lock keepers as other areas not mentioned in this notice may be affected as well.
Please check our website for regular updates and further information on these works which will be taking place.
Once we have a more accurate idea of the dates we will be commencing the dredging works, this notice will be updated straight away.
Enquiries: Newark – 0303 040 4040
Restriction: River Severn
River Severn
Thursday 2 May 2013 until further notice
Please be advised that a landslip has occurred approximately 300 yards upstream from Bevere Lock on the River Severn. The dimensions of the landslip are 50meters in width and extends approximately 10meters into the navigation, a tree has also fallen opposite the landslip meaning that the River width is restricted.
Please take caution here when passing traffic in the opposite direction.
Canal and River Trust Apologise for any disruption.
Enquiries: 03030404040
Advice: Shropshire Union Canal
AUDLEM SERVICES CLOSED – DUE TO DRAINAGE PROBLEM
Monday 29 April 2013 until further notice
The services at Audlem are CLOSED until further notice due to problem with the drainage.
A further update will follow as soon as available.
The nearest Canal & River Trust services are located at Nantwich if heading North or Market Drayton if heading South.
The Canal & River Trust apologise for any inconvenience caused.
Enquiries: 0303 040 4040
Stoppage: River Trent
Between Cromwell Lock and Nether Lock
Wednesday 24 April 2013 until further notice
Due to a serious incident which has taken place, we have had to close the navigation between Cromwell Lock and Nether Lock.
Boaters are not allowed to travel along the navigation until the situation has been dealt with.
We apologise for any inconvenience this may cause and will try to have the navigation open again as soon as possible.
Please check our website for regular updates on this stoppage.
Enquiries: Newark – 0303 040 4040
Stoppage: Grand Union Canal
Braunston Lock 3
Thursday 25 April 2013 – Thursday 25 April 2013
The lock will be shut on Thursday 25th April between 8am and 4.30pm to carry out the work required to prevent water loss through the lock gates.
Stoppage: Grand Union Canal
Calcutt Lock 2 Stoppage
Monday 22 April 2013 – Monday 22 April 2013
To allow us to carry out work on reducing water leakage at Calcutt Lock, the lock will be shut on Monday 22nd April 2013 from 8am to 4.30pm.
Enquiries: 0303 0404040
Advice: Shropshire Union Canal
Wheaton Aston Service Block – REOPEN
Thursday 28 March 2013 – Thursday 4 April 2013
UPDATE (04 April 2013): Maintenance works have now been completed and the service block is reopen.
Canal & River Trust apologise for any inconvenience caused.
Amended Advice: River Trent
Non Tidal Section of the Trent
Wednesday 16 February 2011 until further notice
UPDATE (04 April 2013): Following a review of our planned spend for 2011/12 we have chosen to reduce the hours our lock keepers will be in attendance at the non-tidal River Trent Locks from the current hours of 9:30am to 6:00pm to new hours of 9:30am to 5:30pm.
We have not taken this decision lightly and understand it will cause some annoyance and disruption, but in view of reduced national budgets a cut in overtime has been necessary.
I trust you will appreciate this is only a small reduction in hours against a backdrop of much bigger cuts.
We apologise for any inconvenience caused.
We would also like to make customers aware that the locks will be manned for boat passage by the seasonal lock keepers from Good Friday till 31st October each year.
Amended Advice: Shropshire Union Canal
CALVELEY SERVICES – NOW OPEN
Wednesday 3 April 2013 – Wednesday 3 April 2013
UPDATE (03 April 2013): The Specialist Cleaning Contractors have attended site and the services have been fully cleaned and are now fully operational again.
The Canal & River Trust apologise for any inconvenience caused.
Advice: Shropshire Union Canal
CALVELEY SERVICES CLOSED DUE TO BLOCKAGE
Wednesday 3 April 2013 until further notice
UPDATE (03 April 2013): Canal & River Trust staff have attended site and removed the top from a toilet cassette which had caused the blockage to the Elsan system.
The Elsan Facility is now operational but the Showers and Toilets still remain closed until a Full Clean is carried out by specialist contractors.
An update will follow once this has been carried out.
Customer reminder – Please ensure care is taken when using the Elsan disposal facility to prevent foreign objects causing blockages to the drainage system.
Thank you
Advice: Shropshire Union Canal
CALVELEY SERVICES CLOSED DUE TO BLOCKAGE
Wednesday 3 April 2013 until further notice
There is a blockage in the pipework to the Elsan and toilets and therefore all facilities at this service block have been closed until further notice.
Contractors have been called and will attend site as soon as possible.
An update will follow as soon as available. The nearest Canal & River Trust services are located at Chester if heading North or Nantwich if heading South.
The Canal & River Trust apologise for any inconvenience caused.
Enquiries: 0303 040 4040
Amended Stoppage: Shropshire Union Canal
Near bridge 66 (Betton Wood)
Monday 25 March 2013 – Wednesday 3 April 2013
UPDATE (03 April 2013): The canal is now fully open to navigation.
The Canal & River Trust apologise for any inconvenience caused.
Stoppage history:
UPDATE (26 March 2013): Please be advised that the area by Bridge 66 is now ‘passable with care’.
Contractors will be on site today to remove the tree.
We apologies for any inconvenience which may have been caused.
Opening Times: Trent & Mersey Canal
ANDERTON BOAT LIFT – Summer Opening Times 2013
Thursday 21 March 2013 – Sunday 3 November 2013
Anderton Boat Lift will run to a seasonal schedule with private passage available at various
points of the day, these will vary due to schedule, demand and availability.
Passage available during these times: (directional time restrictions apply)
OFF-PEAK Monday – Friday 09:30am – 16:30pm
PEAK Saturday & Sundays, Bank Holidays & August 09:30am – 17:30pm
Bookings can be made by calling the bookings team on 01606 786 777 option 8, or by visiting the booking office.
Enquiries: 01606 786777
Stoppage: Staffordshire & Worcestershire Canal
Bridge 59 Compton Bridge, Bridgnorth Road, Compton, Wolverhampton
Tuesday 2 April 2013 – Tuesday 30 April 2013
UPDATE (03 April 2013): It has been necessary to erect scaffolding across the canal to support the pipe bridge. The navigational width has been reduced to 2.5 metres and the air-draft has been reduced to 2.4 metres. Please approach with care.
Advice: River Severn
River Severn Between Upton on Severn & Worcester
Tuesday 2 April 2013 until further notice
A bank slip has occurred on the River Severn where the Riverside Caravan Park fronts the river.
Information received, but as yet to be verified, has indicated that the slip has partially obstructed the river channel and that there are submerged objects.
Boaters are requested to approach the area with extreme caution, keep a careful watch and ensure that they do not stray from the navigation channel (ie the middle third of the river).
Further information can be obtained by contacting the Canal and River Trust.
Enquiries: 03030 404040
Restriction: Trent & Mersey Canal
Bridge 103, Plume of Feathers bridge
Monday 8 April 2013 – Friday 10 May 2013
Contractors working on behalf of Staffordshire County Council will be undertaking painting works to the footbridge and railings which cross the Trent & Mersey Canal at Plume of Feathers bridge. The works will require a floating pontoon to afford access to the underside of the structure. A banks-man will be positioned on the bridge to look out for any approaching craft; in which case the pontoon will be re-located to allow passage.
Please approach the site with caution.
Canal & River Trust apologise for any inconvenience this may cause.
Enquiries: 0303 040 4040 during normal office hours.
Amended Stoppage: River Severn
River Severn
Thursday 28 March 2013 until further notice
UPDATE (01 April 2013): Please be advised that due to receeding water levels all lock are now open.
Canal & River Trust are sorry for any inconvenience that this may have caused.
Amended Stoppage: Huddersfield Narrow Canal
Lock 32W – Diggle flight
Monday 11 March 2013 – Friday 26 April 2013
UPDATE (28 March 2013): Unfortunately the damaged lock gate has not yet been removed from the lock due to access issues with the land owners. Temporary road access is required and we cannot do this without crossing other peoples land and permission has not been given yet.
Unfortunately, as it is a single leaf tail gate it will not fit in a boat and this is therefore the only way to get it out.
We believe the gate will be removed next Thursday 4th April when it will be taken to our workshop and we expect, will be returned a fortnight after that. If we become aware that the workshop will take longer to repair than expected, we will update this notice.
Our revised plan is for the navigation to re-open on 26th April.
We are disappointed about this delay and can only apologise to customers who have been affected by an situation outside of our control.
We will be contacting customers who have bookings for the Standedge Tunnel to reschedule.
Please note that Lock 30E has re-opened and anyone wishing to transit the tunnel and moor above Lock 32W can do so.
Canal & River Trust apologise for the inconvenience caused.
Amended Stoppage: Llangollen Canal
Between Llangollen and Glenrid Bridge No.19
Friday 22 March 2013 – Thursday 28 March 2013
UPDATE (28 March 2013): The canal has now reopen. However please proceed with care north between Chirk Bank and Llangollen. This is due to an amount of debris remaining on the towpath and within the canal channel. This will be removed in due course.
We apologise for any inconvenience which may have been caused.
Advice: Shropshire Union Canal
Norbury Junction Service station
Monday 25 March 2013 – Thursday 28 March 2013
UPDATE (28 March 2013): Repairs have been completed and the Service Station has now reopen.
We apologise for any inconvenience which may have been caused.
Stoppage: River Severn
River Severn
Thursday 28 March 2013 until further notice
UPDATE (28 March 2013): Updated 28th March 2013
Please be advised that Gloucester Lock and Upper Lode Lock on the River Severn are on amber alert.
All other locks on the River Severn are open.
This means that the river conditions are hazardous due to strong flows and debris. Boaters are advised to proceed with caution and only travel if safe to do so.
Please contact the lock keeper at Gloucester for updates 01452 310832 . Canal & River Trust are sorry for any inconvenience this may cause.
Advice: Shropshire Union Canal
Wheaton Aston Service Block – Closed until further notice
Thursday 28 March 2013 until further notice
Due to essential maintenance works the service block is closed until further notice. Updates will follow as work progresses.
The nearest Canal & River Trust pump out facility is located at Market Drayton if heading North or Non- Canal & River Trust at Norbury Wharf if heading North and Autherley Junction if heading South which is a private boat yard. The next available Canal & River Trust pump out facility if heading onto the Staffs & Worcs Canal is at Gailey (If heading North) & Kinver (If heading South), there is also an Elsan only Facility at Greensforge Lock 16 which is before Kinver if heading South.
The Canal & River Trust apologise for any inconvenience caused.
Enquiries: 0303 040 4040
Advice: Coventry Canal
Hopwas School Bridge, Thomas Barnes School, Hopwas
Monday 8 April 2013 – Friday 28 June 2013
Staffordshire Council will be carrying out building works to Thomas Barnes School. To carry out the works access is required to the back of the school, therefore the towpath will be used for vehicular access for approx. 50m from Hopwas School Bridge.
Waterway users will maintain priority over the works therefore causing minimal disruption to the canal users. Warning signs will also be placed 50m either side of the worksite with banks men in place during vehicle movement on site.
No heavy commercial vehicles allowed on the towpath.
Canal & River Trust apologise for any inconvenience caused.
Restriction: Grand Union Canal
Winkwell Swing Bridge Restricted opening times
Wednesday 27 March 2013 until further notice
The Winkwell Swing Bridge has a fault and can only be opened manually by Canal & River Trust staff. Staff will be at Winkwell Swing Bridge at 9am, 12noon and 4pm to open the bridge, outside of these times you will not be able to pass the bridge. Please wait for Canal and River Trust staff to be at site and assit you with the bridge.
Enquiries: 0303 0404040
Towpath Closure only: Staffordshire & Worcestershire Canal
Bridge 59 Compton Bridge, Bridgnorth Road, Compton, Wolverhampton
Tuesday 2 April 2013 – Tuesday 30 April 2013
Severn Trent Water has an existing pipe bridge crossing the canal at Compton Bridge, Wolverhampton, transporting clean water. Unfortunately, a burst has occurred within a concrete abutment which requires urgent attention before it worsens. Due to health and safety requirements the towpath will have to be closed in order for the repair to take place. A localised diversion will be in place for pedestrians to follow with signage present. Cyclists are asked to slow down upon approach and adhere to any instruction given by the contractors at the time.
Canal & River Trust apologise for any inconvenience this may cause.
Enquiries: 0303 040 4040
Restriction: River Trent
40m upstream of Newark Town Lock, offside location. Opposite Newark Workshops.
Tuesday 7 May 2013 – Wednesday 31 July 2013
Contractors working to convert and refurbish the egg packers warehouse will be working from a scaffolding platform which projects 1m into the navigation.
The scaffolding will be fully signed and lit upon approach from both sides.
We apologise for any inconvenience which may be caused.
Boaters are asked to reduce speed and pass the site with caution.
Enquiries: Jon Pritchett 0303 040 4040
Stoppage: Shropshire Union Canal
Near bridge 66 (Betton Wood)
Monday 25 March 2013 until further notice
UPDATE (26 March 2013): Please be advised that the area by Bridge 66 is now ‘passable with care’.
Contractors will be on site today to remove the tree.
We apologies for any inconvenience which may have been caused.
Stoppage: River Severn
River Severn
Monday 25 March 2013 until further notice
Please be advised that Gloucester Lock, Upper Lode Lock and Diglis Lock on the River Severn are closed due to high water Levels.
Holt Lock, Bevere Lock and Lincomb Lock are running high and are on amber alert.
This means that the river conditions are hazardous due to strong flows and debris. Boaters are advised to proceed with caution and only travel if safe to do so.
Please contact the lock keeper at Gloucester for updates 01452 310832 . Canal & River Trust are sorry for any inconvenience this may cause.
Gloucester Lock
Tuesday 26 March 2013 – Tuesday 26 March 2013
Canal and River Trust will be carrying out essential maintenance works to Gloucester Lock requiring us to close the lock.
Boats needing to transfer from Gloucester Dock Basin to the River Severn and vice versa are advised that the lock will be open between the following times.
08:00 until 08:30 and 17:30 until 18:00
Divers will be in attendance to undertake the repairs and boaters are requested to take note of the warning signs that will be displayed when manoeuvring in the dock basin.
Canal and River Trust apologise for any inconvenience this may cause
Stoppage: Llangollen Canal
Between Llangollen and Glenrid Bridge No.19
Friday 22 March 2013 until further notice
Due to numerous branches brought down by heavy snow between Llangollen and Glenrid Bridge No. 19, this top section of the Llangollen canal is impassable.
With the present weather conditions & forecast the canal will be closed until Monday next week before the ground conditions improve for our staff to safely remove the obstructions.
We apologise for any inconvenience which may have been caused
Enquiries: 0303 040 4040
Stoppage: Llangollen Canal
Between Trevor and Llangollen
Friday 22 March 2013 until further notice
Due to numerous branches brought down by heavy snow between Trevor & Llangollen, this top section of the Llangollen canal is impassable.
With the present weather conditions & forecast the canal will be closed until Monday next week before the ground conditions improve for our staff to safely remove the obstructions.
We apologise for any inconvenience which may have been caused
Enquiries: 0303 040 4040
Stoppage: Shropshire Union Canal
Near Bridge 30 (Castle Cutting Bridge), Gnosall
Friday 22 March 2013 until further notice
Due to one fallen tree, the canal is blocked to navigation. Contractors have been called and this obstruction will be cleared as soon as possible and an update will then be issued. The Canal & River Trust apologise for any inconvenience caused.
Turning points are Norbury Junction if going South & Wheaton Aston if going North
Enquiries: 0303 040 4040
Opening Times: Montgomery Canal
Frankton Locks – SUMMER OPENING TIMES 2013
Wednesday 27 March 2013 – Thursday 31 October 2013
Lock opening times 12 noon until 2pm, 7 days per week (including Bank holidays).
Bookings are required for passage through the locks.
Customers can book any day in advance but no later than 10.00am on the day of passage*
To book, please call our Northwich Office.
Please note there are no passages available without a booking or outside these hours.
To book a passage Monday-Friday, call 0303 040 4040
If you are calling on a Sat, Sun or Bank Holiday, please call 01606 786777, Option 8 (Anderton Boat Lift)
*NB Customers are advised that there are a maximum of 12 boats allowed down the locks and 12 boats allowed up the locks in any one day and booking well in advance is recommended to avoid disappointment. There is a minimum of 1 night and a maximum of 14 nights stay.
Enquiries: 0303 040 4040
Stoppage: River Severn
Upper Lode Lock – River Severn
Monday 18 March 2013 – Wednesday 20 March 2013
UPDATE (20 March 2013): River Severn River Levels
Please be advised that Upper Lode Lock is now open.
Gloucester Lock is running high and is on amber alert.
This means that the river conditions are hazardous due to strong flows and debris. Boaters are advised to proceed with caution and only travel if safe to do so.
Please contact the lock keeper at Gloucester for updates 01452 310832 . Canal & River Trust are sorry for any inconvenience this may cause.
Stoppage: River Trent
Newark Flood Gates
Monday 18 March 2013 until further notice
Due to the River Trent going into flood, we have had to close Newark Flood Gates.
Boaters are asked not to travel along the navigation until further notice.
We apologise for any inconvenience which may be caused.
Stoppage: River Severn
Upper Lode Lock – River Severn
Monday 18 March 2013 until further notice
River Severn River Levels – Please be advised that Upper Lode Lock is now closed due to high water levels.
The Locks above Upper Lode Lock are still open
Gloucester Lock is running high and is on amber alert.
This means that the river conditions are hazardous due to strong flows and debris. Boaters are advised to proceed with caution and only travel if safe to do so.
Please contact the lock keeper at Gloucester for updates 01452 310832 . Canal & River Trust are sorry for any inconvenience this may cause.
Stoppage: Coventry Canal
Lock 13 Glascote Bottom Lock
Thursday 21 March 2013 – Thursday 21 March 2013
Following an inspection, urgent works are required to the top end offside sluice chamber to remove a blockage prior to the Easter holidays. Unfortunately, the canal will be closed for 1 day from 7am to allow these repairs to be undertaken. Canal & River Trust apologise for any inconvenience this may cause.